Work is cracking on apace at the new Fulfilment Centre.  The new pallet racking is being installed and the new articulated forklift is due to be delivered any day. We can then co-ordinate the re-housing of the stock in it’s new locations ready for the next stage of the development.

Work has also started on the main pick/pack fulfilment centre – the walls are up and the suspended ceiling wires installed.  The heating and air con engineer is here tomorrow to do the prep work for the air con cassettes being installed.